Question 1

Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type. You need to ensure that the project does not contain over-allocated resources. Which feature should you use?

Question 2

In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information:
-Tasks that are not started.
-Tasks in progress.
-Tasks that have finished.
-Total remaining effort for each group of tasks.
What should you do on the View tab?

Question 3

You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?

Question 4

You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?

Question 5

The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?