Question 1

You are a project manager in an organization that uses Microsoft PPM.
You have been given additional responsibilities managing existing projects created by another project manager.
When reviewing the project plan, you observe that some of the upcoming tasks are assigned to a generic resource.
You need to update the generic tasks to use defined resources.
Which type of resource should you use?

Question 2

This question requires that you evaluate the underlined text to determine if it is correct.
To review the resource engagements requested by a project manager, the resource manager can navigate to the Resource Requests page and accept or reject the requests.
Review the underlined text. If it makes the statement correct, select "No change is needed."
If the statement is incorrect, select the answer choice that makes the statement correct.

Question 3

HOTSPOT
A project that you manage begins to go over budget.
You need to reduce the scope of the project and retain a baseline record for all tasks.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.

Question 4

You are a portfolio manager for an organization that uses Microsoft PPM to manage projects. You plan to implement Power BI.
You need to import into Power BI by using the Microsoft Project Online content pack.
What should you do?

Question 5

DRAG DROP
You are a program manager who is using Microsoft PPM and Microsoft Project to manage an e-commerce portal development program.
The program is separated into individual projects that represent each area of development, so that each group can manage its own tasks while still having progress visibility at the program level.
You need to be able to manage the overall program as well as its associated individual projects within Project Center. This includes the project sites associated with both the program and the individual projects. Each individual project site should be a subsite of the overall program project site.
You need to create the master program, the individual projects, and their associated project sites.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.