This question requires that you evaluate the underlined text to determine if it is correct.
You are managing community service efforts for a group of college students in a group named Student by using Microsoft Project. You create a task named Community Cleanup.
You set the value of the Duration field to 5 days and the value for the Work field to 400 hours. If you set the value for the task type field to Fixed Work and add the Student resource to the task, the equivalent of 10 college students are assigned to the task.
Review the underlined text. If it makes the statement correct, select "No change is needed." If the statement is incorrect, select the answer choice that makes the statement correct.
You are a project manager, and your organization uses Project Professional 2013.
You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.
You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.
What should you do?
Your organization uses Project Professional 2013.
A senior stakeholder in a project asks you to determine when a task is over budget by comparing the baseline cost of a task to the cost. Additionally, the senior stakeholder wants you to display a graphic indicator when the baseline cost is greater than the cost.
You write a formula to display the indicator, but it only displays for normal tasks and not for summary tasks.
You need to make the indicator display for summary tasks.
Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)
You are a project manager who uses Project Professional 2013.
You manage a critical project, which involves many team members. You are the only team member who has Project Professional 2013. You need to receive updates from team members directly from Microsoft SharePoint without having to reenter the updates in your project.
What should you do?
You manage a project by using Project Professional 2013.
The work variance for a task is 48 hours. The remaining work is 25 hours. The work for this task has been completed.
You need the work variance to be adjusted to reflect what has occurred during the performance of the task.
What should you do?