Question 1
Which two statements describe how the Resource Qualification Score is calculated?
Question 2
Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified that their cost spread distribution factor on a 10 spread point scale resembles:
0-4-10-11-14-13-10-4-0-0. Identify two ways to handle this kind of a spread on their budgets and forecasts. ( Choose two)
0-4-10-11-14-13-10-4-0-0. Identify two ways to handle this kind of a spread on their budgets and forecasts. ( Choose two)
Question 3
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project:
Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want todefine deliverables for your project requirementsthat are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)
Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want todefine deliverables for your project requirementsthat are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)
Question 4
Yourcustomer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)
Question 5
You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)