As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. Which three are parameters that are based on which the system identifies the new resources?
A project administrator is trying to assign a team member for a project but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)
Correct Answer: D
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-foundation-configuration-define-project-resource-breakdown-structures.html#OAPFM180158_2 Why can,t I find persons in the list of resources when I enter team members, planning resources, or person rate schedules? You can,t find persons in the list of resources when you enter team members, planning resources, or person rate schedules in the following situations: The administrator didn,t assign a department while creating users. Persons must have an active assignment and be assigned to a department in Oracle Fusion Human Capital Management before they can be added as team members or entered as resources on the planning resource breakdown structure or person rate schedule. The resource isn,t active in Oracle Fusion Human Capital Management because the current date is before the effective date of the resource. If you want to include persons who will start in the future, select the Include people with future-dated effective start dates option when you search for the person. Persons assigned as project managers aren,t active as of the project start date. The assignment of the person is terminated, and an appropriate value isn,t set for the number of days to display people with terminated assignments. You can set the profile value appropriately at the site profile level using the Specify Number of Days to Display People with Terminated Assignments task in the Setup and Maintenance work area.
Question 38
Which two statements are true about the cross-charge method, Borrowed and Lent?
Correct Answer: A
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjc/process-project-cost-transactions.html#OAPJC284872 What,s a borrowed and lent processing method? A method of processing cross-charge transactions that generates accounting entries to share revenue or transfer costs from the provider organization to the receiver organization within a legal entity. An internal invoice isn,t created but costs or revenue are shared based on the transfer price rules. This method provides a financial view of the performance of an organization.
Question 39
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client''s expectations. Identify two valid rules based on which cost association works.
Correct Answer: C
Reference https://docs.oracle.com/cd/E37583_01/doc.1116/e22598/F458900AN13D82.htm How Resource Mapping Is Calculated You can track the cost impact of every resource that has been assigned to a project task and use the resource breakdown structure to view the breakdown of these costs. Oracle Fusion Projects associates the costs of the resources used for tasks with branches and levels in the resource breakdown structure. The process for determining the correct association is managed by rules of precedence. Oracle Fusion Projects uses the following rules to associate cost amounts with resources: Select the lowest level in the resource breakdown structure to which a transaction can map. If there is only one level to which the transaction maps, the cost amounts are mapped to that level. If the transaction maps to more than one level, Oracle Fusion Projects sums the precedence numbers for all resource types in the branch and gives precedence to the resource element in the branch with the lowest sum. If more than one branch has the lowest precedence number at the lower level, the application uses the precedence number of the next level up. If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with the lowest number at the lowest level. If one branch contains a user-defined resource type, precedence is given to the branch that does not contain a user-defined resource type. Note Oracle Fusion Projects gives more precedence to a lower precedence number. For example, a resource element with a precedence number of 1 is given precedence over a resource element with a precedence number of 10.
Question 40
Which precedence order is used by the system for labor schedules to distribute payroll cost?
Correct Answer: B
The precedence order that is used by the system for labor schedules to distribute payroll cost is Assignment > Assignment Element > Element. This means that the system first looks for a labor schedule that is assigned to the employee assignment, then for a labor schedule that is assigned to the payroll element of the employee assignment, and finally for a labor schedule that is assigned to the payroll element itself. The system uses the first labor schedule that it finds in this order to distribute the payroll cost to projects and tasks based on the hours and rates defined in the schedule. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2356121