Question 1
Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is assigned to the work center W1. There are five units of LATHE available, of which three units are available for the MorningShift and the remaining units are available for the Evening Shits.
Which two actions must you perform to associate LATHE with W1?
Which two actions must you perform to associate LATHE with W1?
Question 2
Identify three requirements fulfilled by nonstandard work orders.
Question 3
During a Manufacturing Cloud implementation, the customer request to develop Oracle Transactional Business Intelligence reports that are not available out-of- the box.
Identify the tool that is available to the Report Developer in Manufacturing Cloud to develop the reports.
Identify the tool that is available to the Report Developer in Manufacturing Cloud to develop the reports.
Question 4
A customer has a distribution warehouse (DW) for After Sales and Service and an in-house manufacturing plant (MP). Sales orders are created and shipped from DW.
Identify the two Sourcing Rules that need to be set for order promising to schedule the order.
Identify the two Sourcing Rules that need to be set for order promising to schedule the order.
Question 5
A plantruns 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours.
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?