Question 1

While creating an item in Product Information Management (PIM), the following two item templates are selected in sequence and applied.
1. Template: Finished Goods (WIP = No, Customer Ordered =Yes)
2. Template: Sub-assembly (WIP = Yes, Customer Ordered = No)
Identify the Item Attribute values in the application.
  • Question 2

    Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM) and Order promising (GOP), which must be set to process the Back-to-Back order with Make Supply Order, for a nonstocked item.
  • Question 3

    A production Supervisor has noticed that Work Orders created manually are overwritten by the plan runs executed by Planning Central. After discussing this issue with the Planner, two actions are recommended to prevent the Work Orders from being overwritten by plan runs.
    Identify the two recommendations.
  • Question 4

    A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
    Determine the available capacity of the resource R1 for thatweek.
  • Question 5

    In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required.
    A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting.
    Identify three process steps that the cost accountant has to perform to transferthe assembly to cost accounting in frozen type.