Question 1

Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where
actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.

Question 2

You have been asked to set up cost estimates for 10 different purchased items. Which two steps could be used
to accomplish this task?

Question 3

The Manufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You
associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to
assign all units of resource R2 available for Day and Night Shift.
Identify the correct sequence of steps to achieve this requirement.

Question 4

You can generate and manage work order exceptions in Oracle Manufacturing Cloud. Which users can report
production exception and who gets notified after an exception is raised?

Question 5

In a manufacturing plant, a production operator in a given shift completes a car assembly and reports this using
orderless completion by referencing a Work Definition.
Identify the two purposes of the referenced Work Definition in Orderless reporting.