Question 1

Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)

Question 2

Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)

Question 3

You search for resources to fulfill a project resource request but are unable to proceed after receiving the following error message: "The search for resources cannot be completed because the project resource search index is not available. Contact your help desk." Identify the cause for this error message. (Choose the best answer.)

Question 4

Which two statements are true about the cross-charge method, Borrowed and Lent?

Question 5

You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)