Question 1

Your customer has set up a contract project with a distribution rule Work/Work. Identify three setup options to:
- Charge labortransactions revenue and all othernonlabortransactionsrevenue to separate accounts
- Generate separate invoice lineamountsforlaborand nonlabortransactions

Question 2

You implement Project Manufacturing along with Project Costing for manufacturing company. You define various expenditure types in which few are specific to Project Manufacturing. Identify the three setups that are required to have an expenditure type specific to Project Manufacturing.

Question 3

You define assets for your project and assign them at the project or task level. What should be the value of "Project Asset Type" to generate asset lines?

Question 4

A client requires a project definition that allows for charging expenditures to the project at a higher Work Breakdown Structure level than where the manually entered percentage complete progress is captured. Which three Shared Structure relationships will support this requirement?

Question 5

Refer to the exhibit.

In your company's Expenditure/Event Organization Hierarchy, organization labor costing rules are assigned to all organizations except San Jose. What happens when you run the "PRC: Distribute labor costs" program for a timecard transaction entered by an employee from the San Jose organization?