Question 11

Your customer has separate organizations to maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (Choose two.)
  • Question 12

    You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
  • Question 13

    You have four resources in your organization: P, Q, R, and S.
    Resource P - Project or resource calendar is active.
    Resource Q - Project resource request dates are within the project or resource calendar effective dates.
    Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
    Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
    Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
  • Question 14

    You have been asked to set up one active person, who is not a team member in the project, as a quality manager for each quality task created under projects. However, when you try to assign the quality manager as Task Manager, you cannot find the person's name in the list of values. What is the reason for this problem?
    (Choose the best answer.)
  • Question 15

    You have a billable project for which the following details are provided:
    Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
    Associated Project Budgeted Cost: USD 300
    Contract Amount: USD 1000
    Project Funded Amount: USD 750
    Sum of Existing Revenue Events: USD 80
    Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)