Question 21

Where is the Allow Override option for the Default Capitalized Interest Rate Schedule specified?
  • Question 22

    You have a billable project for which the following details are provided:
    Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
    Associated Project Budgeted Cost: USD 300
    Contract Amount: USD 1000
    Project Funded Amount: USD 750
    Sum of Existing Revenue Events: USD 80
    Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
  • Question 23

    While creating a new project template, you notice that a default Asset Cost Allocation method is being automatically associated. Identify the source setup from which the default value is being inherited. (Choose the best answer.)
  • Question 24

    You have four resources in your organization: P, Q, R, and S.
    Resource P - Project or resource calendar is active.
    Resource Q - Project resource request dates are within the project or resource calendar effective dates.
    Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
    Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
    Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
  • Question 25

    Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)