Question 6

Which is NOT a required setup task for Manufacturing master data?
  • Question 7

    In a manufacturing plant, two purchase components, PI and P2, and a resource, Rl, are required to assemble a product. The cost of the assembly is calculated by using the standard costing method. The work definition and resource rates for the assembly have been defined as Required.
    A Cost Accountant is estimating cost of the assembly, and analyzing rolled-up costs before finally publishing estimates as frozen standards to Cost Accounting by using a Cost Planning Scenario. While reviewing rolled-up costs, the extended costs of purchase components are not included in a rolled-up scenario.
    What is the reason for this?
  • Question 8

    Which option represents all the production exception types that can be reported by a Production Operator in Oracle Manufacturing Cloud?
  • Question 9

    Your client's company is in a regulated industries and must keep detailed records of their product manufacturing processes in accordance with the United States Food and Drug Administration (FDA) regulation on electronic records and signatures called 21 Code of Federal Regulations (CFR) Part 11.
    You are implementing Oracle E-Signatures and E-Records for securely capturing, storing, retrieving, and printing electronic records and signatures in manufacturing. They enable Deferred Electronic Records and Electronic Signatures for Manufacturing Work Order Release in Oracle Manufacturing Cloud.
    Which statement is NOT true about using Deferred Electronic Records and Electronic Signatures for Manufacturing Work Order Release?
  • Question 10

    The pick release of a project work order creates movement requests with the project and the task from the work order.
    Which statement is NOT true about this?