You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)
You are trying to create a project purchase order (PO) but you are unable to select Expenditure Organization in the PO. Identify two reasons for this problem. (Choose two.)
Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of
01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)