Question 1
An architect is designing a new backup solution for a vSphere platform that has been recently upgraded to vSphere 7.
The architect wants the backup solution to perform the following:
Full virtual machine image backup and restore
Incremental virtual machine image backup and restore
File level backup and restore within both Windows and Linux virtual machines LAN-free backup Which functional requirement should the architect include in the design of the new backup solution?
The architect wants the backup solution to perform the following:
Full virtual machine image backup and restore
Incremental virtual machine image backup and restore
File level backup and restore within both Windows and Linux virtual machines LAN-free backup Which functional requirement should the architect include in the design of the new backup solution?
Question 2
What is a benefit of using a scale-out method for handling vSphere cluster growth?
Question 3
Following a recent acquisition, an architect needs to merge IT assets into its current data center. The combined vSphere environment will need to run the newly acquired company's virtual machines.
Network integration work has already been completed and the current environment has capacity to host all virtual machines. The Operations team needs to identify which virtual machines belong to the acquired company and report on their usage.
How should the architect merge the company's assets and virtual machines?
Network integration work has already been completed and the current environment has capacity to host all virtual machines. The Operations team needs to identify which virtual machines belong to the acquired company and report on their usage.
How should the architect merge the company's assets and virtual machines?
Question 4
An architect is tasked with designing a greenfield VMware software-defined data center (SDDC) solution that will be used to deliver a private cloud service for a customer.
During the initial meeting with the service owner and business sponsor, the customer has provided the following information to help inform the design:
The solution must initially support the concurrent running of 300 production and 600 development virtual machines.
The production environment should be delivered across two geographically dispersed data centers. The development environment must be vSphere-based but does not have to be deployed on-premises.
The two data centers are connected to each other through multiple diversely routed, high bandwidth and low latency links.
The customer's server hardware standard document states that all virtual infrastructure hosts must be based on blade architecture only.
The service owner has said that is important to ensure that neither the availability target of 99.5% nor the resource capacity is affected when the operations team completes maintenance activities, such as the monthly software patching and ad-hoc hardware break/fix.
All virtual machine backups must be completed using the existing backup service. The recovery time objective (RTO) for the service is four hours.
The recovery point objective (RPO) of the service is 24 hours.
Given the information from the customer, which two would be classified as assumptions within the design? (Choose two.)
During the initial meeting with the service owner and business sponsor, the customer has provided the following information to help inform the design:
The solution must initially support the concurrent running of 300 production and 600 development virtual machines.
The production environment should be delivered across two geographically dispersed data centers. The development environment must be vSphere-based but does not have to be deployed on-premises.
The two data centers are connected to each other through multiple diversely routed, high bandwidth and low latency links.
The customer's server hardware standard document states that all virtual infrastructure hosts must be based on blade architecture only.
The service owner has said that is important to ensure that neither the availability target of 99.5% nor the resource capacity is affected when the operations team completes maintenance activities, such as the monthly software patching and ad-hoc hardware break/fix.
All virtual machine backups must be completed using the existing backup service. The recovery time objective (RTO) for the service is four hours.
The recovery point objective (RPO) of the service is 24 hours.
Given the information from the customer, which two would be classified as assumptions within the design? (Choose two.)
Question 5
A new real-time financial service application is being developed by the engineering team at a financial firm and will be released as a public Software-as-a-Service (SaaS) offering. The solutions architect has designed and deployed a new vSphere environment and the supporting network infrastructure for hosting all public services. ESXi hosts are configured to use Precision Time Protocol (PTP) and a local stratum-1 network time server.
Application provisioning and scaling will be managed by VMware vRealize Automation and can be run on Microsoft Windows or multiple distributions of Linux.
Which three recommendations should the architect include in the design to ensure that the service maintain timekeeping within an accuracy of one second? (Choose three.)
Application provisioning and scaling will be managed by VMware vRealize Automation and can be run on Microsoft Windows or multiple distributions of Linux.
Which three recommendations should the architect include in the design to ensure that the service maintain timekeeping within an accuracy of one second? (Choose three.)