Question 1

You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?

Question 2

You enter the finish date for a task, and then assign a resource. You discover that the task is automatically scheduled for two weeks past the finish date you have entered. You need to identify the problem. What should you do?

Question 3

Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do?

Question 4

You update your project schedule based on information received from your team members in today's status meeting. You need to compare the current revised project schedule with the baseline schedule side by side. Which default view should you use?

Question 5

You have a list of tasks in Microsoft Excel 2010. You need to create a Microsoft Project 2010 schedule that maintains the order of the tasks. Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)