Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?
You need to ensure that you can view only the tasks on your projects critical path. What should you do?
Your project contains many tasks that have dependencies and result in independent networks of tasks. You need to ensure that you can view critical tasks on all independent networks of tasks within the project. What should you do?
Standard working hours are eight hours a day from Monday through Friday. You create a task of fixed units
and set the duration to 2 days. You assign the task to John at 100 percent. John wants to work only 50
percent on the task. You change John's assignment units to 50 percent for the task.
Which set of values describes the specified task?