Question 1

You are a project manager, and you use Project 2013 for a large construction project.
You create the work breakdown structure (WBS) and plan to add the following resources for your project: concrete, construction supplies, and airline tickets.
You need to add these resources to your schedule.
Which two resource types should be created for these resource examples? (Each correct answer presents part of the solution. Choose two.)

Question 2

This question requires that you evaluate the underlined text to determine if it is correct.
You are managing community service efforts for a group of college students in a group named Student by using Microsoft Project. You create a task named Community Cleanup.
You set the value of the Duration field to 5 days and the value for the Work field to 400 hours. If you set the value for the task type field to Fixed Work and add the Student resource to the task, the equivalent of 10 college students are assigned to the task.
Review the underlined text. If it makes the statement correct, select "No change is needed." If the statement is incorrect, select the answer choice that makes the statement correct.

Question 3

You are using Microsoft Project Professional 2013.
Three years ago, you successfully completed a project to review all of the suppliers within your organization, and you have been asked to run a similar project again. You still have the project plan from three years ago.
You need to use the most efficient method to produce a new plan with tasks based upon the old project plan.
What should you do?

Question 4

You are a manager for an organization that uses Project Professional 2013.
A critical project shows average finish variance values between 5-10 days for the tasks.
You need to interpret these variance values to determine the next course of action to take.
What do these variance values mean?

Question 5

Your organization uses Project Professional 2013.
You are setting up a preliminary schedule by using manually scheduled tasks.
As you build the task breakdown, you notice a potential scheduling problem indicated by a wavy red line under the finish date of a detail task.
You need to determine the cause of the wavy red line.
What should you do?