Question 36

Which of the following are NOT normally included in the project scope statement, either directly or by reference?
  • Question 37

    You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
  • Question 38

    Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?
  • Question 39

    Which is NOT an industry-recognized methodology for quantifying critical delay?
  • Question 40

    Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?