You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?
Your organization has decided to augment your testing team with an offshore team. The offshore team members are experienced testers who are experts in the domain of the system under test Your team isworried about the offshore team taking their jobs and they are resistant to the change You need to pick three of your team members to be the ambassadors for the new team Which competences will be most important for your ambassadors to possess?
You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.
Given this information what should you conclude?
You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?