Which of the phases in the AgilePM project lifecycle is optional?
Correct Answer: A
The AgilePM lifecycle typically includes Pre-Project, Feasibility, Foundations, Evolutionary Development/Realization, Deployment, and Post-Project (benefits). Feasibility is designed as a lightweight, optional phase to confirm there is a sensible case to proceed before deeper investment. In some contexts-when viability is already established, or scope and constraints are straightforward-Feasibility may be skipped or greatly abbreviated, moving directly to Foundations, where the approach, governance, and baselines are established. By contrast, Foundations is expected for alignment and control, and Realization (timeboxed delivery) is where the solution is built; these are not optional if you are proceeding with delivery. Thus, Feasibility is the optional phase.
Question 2
Which responsibility relates to the role of the Business Ambassador?
Correct Answer: D
The responsibility of the Business Ambassador in AgilePM is to provide day-to-day detail of the requirements during Timeboxes. This role involves representing the interests of the business within the project team, ensuring that the evolving product meets the business needs. The Business Ambassador works closely with the development team to clarify requirements, provide feedback, and make decisions promptly to keep the project on track. Reference: AgilePM Foundation Handbook "Agile Project Management for Dummies" by Mark C. Layton
Question 3
According to Pink, which three factors are key motivators for 'knowledge work'?
Correct Answer: D
* Autonomy, Mastery, and Purpose: As outlined by Daniel Pink, these three factors drive motivation in knowledge work, which relies on creativity and engagement. Agile practices support autonomy through self-organizing teams, mastery through continuous learning, and purpose through shared goals. * Other Options: These reflect traditional or outdated models of motivation and do not align with Pink's framework. Key AgilePM Concepts Referenced: * Motivating Teams: AgilePM Handbook, Chapter 5, Section 5.7.
Question 4
In a free format Timebox, when should reviews take place?
Correct Answer: B
In a free format Timebox, reviews should take place: B. Throughout the body of the Timebox3.
Question 5
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?
Correct Answer: A
The Business Visionary is responsible for interpreting the needs of the Business Sponsor and communicating these to the team1. This role represents the Business Sponsor by communicating the vision of the project and ensuring that the team understands the sponsor's requirements1.