During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re- engage this group and explore discrepancies in understanding.
Is this an appropriate application of Agile Project Management for this project?
Xan Insurance Company is a friendly company with no separate private offices for individual managers. Staff members prefer to wander around the office space and have one-to-one chats rather than use email or have lots of meetings.
What action should the Project Manager take when planning for effective communication throughout the Web project?
Using the additional information provided for this question in the Scenario Booklet, answer the following question about the actions the Sales Director should take to develop an effective Sales management team, according to the five dysfunctions that characterize an ineffective team identified by Patrick Lencioni.
Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
The Web Content Manager has provided the Web Developer with a mock up
of the 'Contact Us' page, to be created for the new coffee bar insurance product. When producing the code, the Web Developer has created a button that reads 'Delete' instead of 'Cancel'.
What action should the Web Content Manager take?