Question 1

You have implemented automatic requirements grouping for projects. Once you check the materials turbine and fittings you realize that the requirements are grouped for turbine but not for fittings. What might be the reason?
Please choose the correct answer.
Response:

Question 2

Where can you define that a network is a "header-account assigned" or "activity-account assigned"?

Question 3

What happens if the appended indicator is not set and an order is appended?
Please choose the correct answer.
Response:

Question 4

Which type of network does not allow you to assign materials directly, but only indirectly using a bill of materials?
Please choose the correct answer.
Response:

Question 5

Which type of down-payment chain allows you to monitor receivables to customers and to gain information on past and future incoming payments?
Please choose the correct answer.
Response: