Question 1

A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
  • Question 2

    You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
  • Question 3

    You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?
  • Question 4

    You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
  • Question 5

    Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.