Question 46

You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
  • Question 47

    Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
  • Question 48

    Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
    What benefit do they have when using delivery from project (CNSO).
  • Question 49

    You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question
  • Question 50

    You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?