Question 91
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question
Question 92
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
Question 93
Materials
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).
Question 94
How can you update the degree of processing for an activity?
Question 95
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?