Question 31
A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Question 32
Which time elements can be reduced by a reduction strategy? Note: There are 3 correct answers to this question.
Question 33
Which materials have a negative quantity in a bill of materials or in a recipe? Note: There are 3 correct answers to this question.
Question 34
The production plan is being disrupted by last minute demands that are entered in the system. Which is the most efficient way to handle last minute demands and protect the current production plan?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Question 35
Which elements are included in the structure of the batch where-used list?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response: