Question 1

You want to trigger inhouse production of a semifinished material before a sales order for the corresponding finished good is received.Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semifinished material?
  • Question 2

    Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?
    Note: There are 2 correct answers to this question
  • Question 3

    Your quality department detects a deviation in a raw material batch. Unfortunately this batch has already been used in production. How can you identify all affected finished goods stocks?
    Note: There are 2 correct answers to this question.
  • Question 4

    What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
  • Question 5

    Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.