A program manager consults with a client on how to improve their BPM Center of Excellence (COE). The program manager asks what metrics are being used to track the success of the COE.
The client offers examples of the metrics that are being collected for several processes related to the cycle time and efficiency. What course of action should the program manager suggest?
The BPM Program Manager, Process Owner, and Lead Developer are collaborating to define the theme and assign user stories for the next iteration. The team is planning the 7th of 15 iterations in the Release Plan for Release One. The Program Manager displays a Team Velocity chart showing that the Development team has shown significant growth in story points accepted from iterations 1 to 4 and has been leveling off to roughly 200 story points in iterations 5 and 6.
Given there are 9 iterations remaining in the release plan, the Process Owner immediately recognizes there is room for roughly 1800 story points in the remaining time for Release One. However, the backlog contains 2400 story points marked as "high" priority and another 1200 story points marked as "medium" priority. The Process Owner asks to reduce the points assessed to the high priority user stories to bring the total points down to roughly 1800 so as to make them fit in the remaining time. The Program Manager agrees.
What is wrong with this scenario?
In the Playback 0 review session, the executive sponsor for BPM suggested adding a requirement to the business process not previously articulated. The executive sponsor would like to see the business requirement implemented by the next playback validation session. How should the program manager handle the previously unknown business requirement?
The BPM validation process is the first time BPM project for the development team. At the project launch meeting, the functional requirements for the project are requested by the developers and administrator. The program manager reminds the team that functional requirements are typically documented during a specific phase in the BPM life cycle. When are the functional requirements for the process documented?