Which of the following is an input into the Develop Project Team process?
Correct Answer: D
Question 232
Which of the following are processes associated with Project Cost Management?
Correct Answer: C
Section: Volume E Explanation/Reference: https://blog.masterofproject.com/cost-management/
Question 233
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
Correct Answer: C
Explanation/Reference: Explanation: Estimate to completion calculates how much more of the budget is needed to complete the project if everything continues at the current level of performance. EAC 'atypical' = AC + BAC - EV EAC 'typical' = AC + ((BAC - EV) / CPI)
Question 234
A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:
Correct Answer: A
Question 235
An output of the Manage Project Team process is:
Correct Answer: A
Section: Volume E Explanation: 9.2.3.3 Project Management Plan Updates Elements of the project management plan that may be updated include, but are not limited to, the human resource management plan. For example, the person assigned to a predefined role may not fulfll all staffing requirements outlined in the human resource management plan. When gaps occur, the project management plan needs to be updated to change the team structure, roles, or responsibilities. Process: 9.4 Manage Project Team Definition: The process of tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance. Key Benefit: The key benefit of this process is that it influences team behavior, manages conflict, resolves issues, and appraises team member performance. Inputs 1. Human resource management plan 2. Project staff assignments 3. Team performance assessments 4. Issue log 5. Work performance reports 6. Organizational process assets Tools & Techniques 1. Observation and conversation 2. Project performance appraisals 3. Conflict management 4. Interpersonal skills Outputs 1. Change requests 2. Project management plan updates 3. Project documents updates 4. Enterprise environmental factors updates 5. Organizational process assets updates