Question 1

____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.
  • Question 2

    A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

    The longest path depends upon relationships driving the timing of activity starts, therefore the following scheduling features should not be used in calculating file longest path.
  • Question 3

    ______________can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.
  • Question 4

    An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
    Answer the question using a straight line depreciation and a 10% interest rate.
    If $50 was invested at 6.0% on January 1, year 1, what would be the value of year-end withdrawals made in equal amounts each year for 10 years and leaving nothing in the fund after the tenth withdrawal?
  • Question 5

    When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?