Question 21
The length of time from when material enters a production facility until it exists, this is known as:
Question 22
The orders are automatically scheduled and controlled by the computer are the orders called:
Question 23
The information for quantities required in manufacturing, planning and control system will come from all of these EXCEPT:
Question 24
Raw materials are recorded into work-in-process, when work is completed and becomes finished goods; the work-in-process inventory is relieved by multiplying the number of units completed by the number of parts in the bill of material, in which system?
Question 25
What is measured by the length of time a product can be used before it fails?