Question 1

Maintainability is:
Response:
  • Question 2

    50 resisters from a lot of 75,000 were tested. The average was 3,306 ohms with a variance of 21,609 ohm 2 . From this information, we may conclude with 99% confidence, that at least 95% of this lot will have resistance values in the range of Response:
  • Question 3

    A company has produced a new module. The failure data on 40 returns are shown below.

    Which of the following is the first step in the review of this situation ?
    Response:
  • Question 4

    You have written what you feel is an excellent book on reliability principles. Your company wants you to conduct company-wide training classes on a specific reliability topic.
    Your advice is sought and you recommend your text because you are familiar with it. What other professional action should be immediately taken?
    Response:
  • Question 5

    System-safety analytical techniques include all EXCEPT:
    Response: