Question 51
The design function which assigns probability of failures between components or subsystems is called:
Response:
Response:
Question 52
A series system whose reliability at 5 hours is 0.80, has three components with these historical constant failure rates:
λ 1 = failure rate for component 1 = 0.04 failures/hour
λ 2 = failure rate for component 2 = 0.07 failures/hour
λ 3 = failure rate for component 3 = 0.01 failures/hour
Three of the four answers are the three component reliabilities at 5 hours. Which is incorrect?
Response:
λ 1 = failure rate for component 1 = 0.04 failures/hour
λ 2 = failure rate for component 2 = 0.07 failures/hour
λ 3 = failure rate for component 3 = 0.01 failures/hour
Three of the four answers are the three component reliabilities at 5 hours. Which is incorrect?
Response:
Question 53
For a company operating multiple units of production equipment, the observed failure rate is 42 x 10-6 failures per operating hour, and the preventive maintenance rate is 320 x 10-6 actions per hour. What is the mean time between corrective and preventive maintenance (MTBM)?
Response:
Response:
Question 54
When assessing failures during a reliability test program, which of the following should a reliability engineer consider first?
Response:
Response:
Question 55
The BEST way to set an overall reliability goal is to:
Response: