Question 11

Which of the following is the BEST course of action when risk is found to be above the acceptable risk appetite?
  • Question 12

    You are the project manager of your enterprise. While performing risk management, you are given a task to identify where your enterprise stand in certain practice and also to suggest the priorities for improvements. Which of the following models would you use to accomplish this task?
  • Question 13

    You are the risk control professional of your enterprise. You have implemented a tool that correlates information from multiple sources. To which of the following do this monitoring tool focuses?
  • Question 14

    An enterprise has identified risk events in a project. While responding to these identified risk events, which among the following stakeholders is MOST important for reviewing risk response options to an IT risk.
  • Question 15

    Which of the following would be a risk practitioner's BEST course of action when a project team has accepted a risk outside the established risk appetite?