Question 221
Which of the following BEST describes the role of the IT risk profile in strategic IT-related decisions?
Question 222
You are the project manager of GHT project. You have identified a risk event on your current project that could save $670,000 in project costs if it occurs. Your organization is considering hiring a vendor to help establish proper project management techniques in order to assure it realizes these savings. Which of the following statements is TRUE for this risk event?
Question 223
Which of the following is the MOST important foundational element of an effective three lines of defense model for an organization?
Question 224
You work as a project manager for BlueWell Inc. Your project is using a new material to construct a large warehouse in your city. This new material is cheaper than traditional building materials, but it takes some time to learn how to use the material properly. You have communicated to the project stakeholders that you will be able to save costs by using the new material, but you will need a few extra weeks to complete training to use the materials. This risk response of learning how to use the new materials can also be known as what term?
Question 225
What should be PRIMARILY responsible for establishing an organization's IT risk culture?