Question 426

John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of which are external to the organization. John needs to make certain that he communicates about risk in the most appropriate method for the external stakeholders. Which project management plan will be the best guide for John to communicate to the external stakeholders?
  • Question 427

    Which of the following BEST indicates the effectiveness of anti-malware software?
  • Question 428

    The BEST key performance indicator (KPI) to measure the effectiveness of a vendor risk management program is the percentage of:
  • Question 429

    The MAIN reason for creating and maintaining a risk register is to:
  • Question 430

    Which of the following is the MOST important component in a risk treatment plan?