Question 351
Which of the following BEST illustrates the relationship of actual risk exposure to appetite?
Question 352
The MAIN reason for creating and maintaining a risk register is to:
Question 353
Which of the following BEST enables the identification of trends in risk levels?
Question 354
You are the project manager of the KJH Project and are working with your project team to plan the risk responses. Consider that your project has a budget of $500,000 and is expected to last six months. Within the KJH Project you have identified a risk event that has a probability of .70 and has a cost impact of
$350,000. When it comes to creating a risk response for this event what is the risk exposure of the event that must be considered for the cost of the risk response?
$350,000. When it comes to creating a risk response for this event what is the risk exposure of the event that must be considered for the cost of the risk response?
Question 355
A key risk indicator (KRI) threshold has reached the alert level, indicating data leakage incidents are highly probable. What should be the risk practitioner's FIRST course of action?