Question 46
A project team member has just identified a new project risk. The risk event is determined to have significant impact but a low probability in the project. Should the risk event happen it'll cause the project to be delayed by three weeks, which will cause new risk in the project. What should the project manager do with the risk event?
Question 47
Which of the following is the BEST indicator of the effectiveness of a control action plan's implementation?
Question 48
Which of the following is MOST important to ensure when continuously monitoring the performance of a client-facing application?
Question 49
An organization has made a decision to purchase a new IT system. During when phase of the system development life cycle (SDLC) will identified risk MOST likely lead to architecture and design trade-offs?
Question 50
What is the BEST information to present to business control owners when justifying costs related to controls?
Premium Bundle
Newest CRISC Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing CRISC Exam! BraindumpsPass.com now offer the updated CRISC exam dumps, the BraindumpsPass.com CRISC exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com CRISC pdf dumps with Exam Engine here: