Question 71
The most encouraged time of day to hold a Scrum Daily Meeting is:
Question 72
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
Question 73
True or False: Scrum Team is self-empowered to do whatever is necessary to achieve sprint goal within organization guidelines.
Question 74
What does the Sprint Backlog consist of?
Question 75
Which system provides evolutionary framework for incremental process improvement?
Premium Bundle
Newest CSM-001 Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing CSM-001 Exam! BraindumpsPass.com now offer the updated CSM-001 exam dumps, the BraindumpsPass.com CSM-001 exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com CSM-001 pdf dumps with Exam Engine here: