Question 56

Test Management
Which of the following statements about management of product quality risks in mature organizations with respect to the lifecycle, is true?
Number of correct responses: 1
K2 1 credit
  • Question 57

    Consider the following test strategies:
    I. Consultative test strategy
    II. Reactive test strategy
    III. Analytical test strategy
    IV. Process-compliant test strategy
    Consider also the following examples of test activities:
    1.Prioritize the test cases, based on the results of a FMEA analysis, to ensure early coverage of the most important areas and discovery of the most important defects during test execution
    2.Execute usability testing driven by the guidance of a sample of users (external to the test team)
    3.Perform exploratory testing sessions throughout the system test phase
    4.On an Agile project, execute tests that cover the test conditions identified for each user story of a feature planned for an iteration
    Which of the following correctly matches each test strategy with an appropriate example?
    K2 1 credit
  • Question 58

    Assume you are working on a defect management process to be used by a software organization to track the current status of the defects reports for several projects.
    When a defect is found for investigation a defect report is created in "Opened" state that is the unique initial state. The defect report status has also a unique finale state that is the "Closed" state.
    The following state transition diagram describes the states of this defect management process:
    Where only the initial ("Opened") and final ("Closed") states are indicated while the remaining states (V, W, X, Y, Z) have yet to be named.

    Which of the following assignments would you expect to best complete the defect management process?
    K3 2 credits
  • Question 59

    Testing Process
    The following are the exit criteria described in the test plan of a software product:
    EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).
    EX2. All test cases in the test suite must be run during the execution phase.
    EX3. Defects are classified into two categories: "C" (critical defect) and "NC" (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.
    Which of the following information is useless when the specified exit criteria is evaluated?
    Number of correct responses: 1
    K2 1 credit
  • Question 60

    Test Management
    You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The project will follow a V-Model software development life cycle and it will have four formal levels of testing: component, integration, system and acceptance testing.
    You must produce the test plan documentation for this project by providing an adequate coordination across the four levels of testing in order to assure auditability.
    Which of the following answers would you expect to best describe how to organize the test plan?
    Number of correct responses: 1
    K3 2 credits