Question 11

Defect Management
Assume you are working on a defect management process to be used by a software organization to track the current status of the defects reports for several projects.
When a defect is found for investigation a defect report is created in "Opened" state that is the unique initial state. The defect report status has also a unique finale state that is the "Closed" state.
The following state transition diagram describes the states of this defect management process:

where only the initial ("Opened") and final ("Closed") states are indicated while the remaining states (V, W, X, Y, Z) have yet to be named.
Which of the following assignments would you expect to best complete the defect management process?
Number of correct responses: 1
K3 2 credits
  • Question 12

    You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:
    I. Availability of re-usable test systems and documentation from previous, similar projects
    II. Unexpected timing of components arrival
    III. Stability of the integration test team (no turnover)
    IV. Many and geographically distributed sub-teams Which of the following statements is true?
    K2 1 credit
  • Question 13

    Assume you are the Test Manager for a new software release of an e-commerce application.
    The server farm consists of six servers providing different capabilities. Each capability is provided through a set of web services.
    The requirements specification document contains several SLAs
    (Service Level Agreements) like the following:
    SLA-001: 99.5 percent of all transactions shall have a response time less than five seconds under a load of up-to 5000 concurrent users
    The main objective is to assure that all the SLAs specified in the requirements specification document will be met before system release. You decide to apply a risk-based testing strategy and an early risk analysis confirms that performance is high risk. You can count on a well-written requirements specification and on a model of the system behavior under various load levels produced by the system architect.
    Which of the following test activities would you expect to be the less important ones to achieve the test objectives in this scenario?
    K4 3 credits
  • Question 14

    Consider the following statements describing the importance of improving the test process:
    I. Test process improvement is important because being focused only on the test process it can provide recommendations to improve the test process itself, but it can't indicate or suggest improvement to areas of the development process
    II. Test process improvement is important because it is much more effective than software process improvement to improve the quality of a software system
    III. Test process improvement is important because several process improvement models (STEP, TPI Next, TMMi) have been developed over the years
    IV. Test process improvement is important because every organization, regardless of the context, should always achieve the maximum level of maturity of testing described in the test improvement models such as TMMi
    Which of the following answers is correct?
    K2 1 credit
  • Question 15

    You are following a risk-based testing strategy. The test execution time is very limited. Assume that all the product risk items require more or less the same level of test effort.

    Which of the following answers describes the best execution schedule in this scenario?
    Number of correct responses: 1
    K3 3 credits