Question 6
Which ONE of the following is an example of a typical "Business-oriented work product"?
Question 7
Which of the following is the BEST way for a test team to keep its independence when working in an Agile development environment?
Question 8
Which one of the following is a testable acceptance criterion?
Question 9
A calculator application is being developed. The third sprint has been planned to add functionality to the calculator to allow scientific calculations.
Which TWO examples below represent activities that would likely be managed on an agile task board for the third sprint?
1) A task to design the features planned for the next sprint.
2) A task to run an acceptance test for a user story.
3) A task to automate regression tests.
4) A task to participate in training in preparation for the fourth sprint.
5) A task to produce a daily progress report for the agile team members.
Which TWO examples below represent activities that would likely be managed on an agile task board for the third sprint?
1) A task to design the features planned for the next sprint.
2) A task to run an acceptance test for a user story.
3) A task to automate regression tests.
4) A task to participate in training in preparation for the fourth sprint.
5) A task to produce a daily progress report for the agile team members.
Question 10
Which of the following is a risk that continuous integration introduces?