Question 277

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a.Any deviation from the procedures described in the test strategy document
b.The overall estimated costs, timescales and resource requirements
c.A detailed schedule of testing activities
d.The development deliverables to be tested
e.Which test staff members (names) will be involved and when
f.Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit
  • Question 278

    Which of the following statements are TRUE? A. Regression testing and acceptance testing are the same. B. Regression tests show if all defects have been resolved. C. Regression tests are typically well-suited for test automation. D. Regression tests are performed to find out if code changes have introduced or uncovered defects. E. Regression tests should be performed in integration testing.
  • Question 279

    Which of the following terms is used to describe the management of software components comprising an integrated system?
  • Question 280

    Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.

    Based on the chart above, what is the most appropriate next test phase? 1 credit
  • Question 281

    Comparing TMMi and TPI, which is not a valid reason for choosing either TPI or TMMi? 2 credits