Question 81
The following settings are defined for a freight order from location A to location B with two freight units:
* The distance between locations A and B in the transportation lane is 1500 km, the duration is 19 hours and the Fix Transportation Duration flag is set. The average speed for the means of transport is defined as 100 km/h and the GIS quality flag is NOT set.
Loading and unloading of each freight unit at locations A and B is defined as 1 hour.
The vehicle resource is available weekdays from 8:00 am to 8:00 pm.
* Loading starts on Monday at 8:30 am. When is unloading finished?
Please choose the correct answer.
* The distance between locations A and B in the transportation lane is 1500 km, the duration is 19 hours and the Fix Transportation Duration flag is set. The average speed for the means of transport is defined as 100 km/h and the GIS quality flag is NOT set.
Loading and unloading of each freight unit at locations A and B is defined as 1 hour.
The vehicle resource is available weekdays from 8:00 am to 8:00 pm.
* Loading starts on Monday at 8:30 am. When is unloading finished?
Please choose the correct answer.
Question 82
In which transaction can you define transportation durations?
Question 83
What is the technology that is used to transfer the master data from ERP to TM?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Question 84
You create a freight settlement document after you plan an inbound delivery with the following items: The total freight costs are USD 3000.
Which posting can be automatically performed for Product 2 if you transfer the freight settlement document with the distributed costs to SAP ERP?
Please choose the correct answer.

Which posting can be automatically performed for Product 2 if you transfer the freight settlement document with the distributed costs to SAP ERP?
Please choose the correct answer.