Question 1

The setup time on the production line to produce a material is extensive. You would like to avoid
multiple setups and limit the production of the material based on a planning calendar.
Which type of lot size procedure should you use to accomplish this?
Please choose the correct answer.
Response:

Question 2

Which of these are layers in SAP Best Practice content?
There are 3 correct answers to this question.
Response:

Question 3

How can you limit the number of master data objects to be created when the manufacturing process is
the same for many different products?
Please choose the correct answer.
Response:

Question 4

The material master of your finished product contains MRP type "PD". You set a manual firming date in
the stock requirements list. Which of the following will firm planned orders"
There are 2 correct answers to this question.
Response:

Question 5

The SAP Kanban procedure could be used to trigger which of the following kinds of replenishment?
There are 2 correct answers to this question.
Response: