Question 61

You run MRP for a material that was planned using Demand-Driven Replenishment. Toward which buffer level does the MRP run create a replenishment proposal?
  • Question 62

    How can you avoid order proposals for planned independent requirements with dates in the past?
    There are 2 correct answers to this question.
    Response:
  • Question 63

    A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
    Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
    Response: