Question 21

In which customizing activity do you set up automatic routing selection production orders?
Please choose the correct answer.
  • Question 22

    In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.
  • Question 23

    How would you define pegging in the context of Advanced Planning?
  • Question 24

    If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?
  • Question 25

    Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.