Question 36

Which object do you configure to reuse material cost estimate for the costing process?
  • Question 37

    You want to run an assessment cycle in Profitability Analysis to allocate cost center costs during period-end closing for your organization. Which of the following objects is part of the assessment cycle?
  • Question 38

    To which objects do you settle values of the results analysis? There are TWO correct answers for this question
  • Question 39

    Which of the following statements best describe Product Cost by Order? Note: There are 2 correct answers to this question.
  • Question 40

    Which activities can you perform while you create cost center hierarchies? There are 2 correct answers to this question