Question 1

A deployment engineer is installing an XE9680 server. The network connectivity has 24 optical cables that route to switches in the data center. The administrator questions the use of a cablemanagement arm (CMA).
What are two items to consider when installing a CMA?

Question 2

A customer wants to implement 20 PowerEdge XE9680 servers for development and rendering of their studio CGI production. The solution includes a shared development environment with multiple outside partners, professionals, and hobbyists.
Due to the heating and cooling limitations of the data center, what GPUs should be used for the servers?