Question 6
You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime. You have chosen table count verification, but not table contents comparison.
Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center, you can see 40 process buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center, you can see 40 process buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
Question 7
What is the minimum SAP_BASIS release of an SAP ECC system that can be converted to an SAP S/4HANA Server?
Question 8
What phases of SUM will be executed during an SAP S/4HANA conversion including DMO?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Question 9
You downloaded content from the SAP note 1000009 ("ASU Toolbox 2008"). Which transaction needs to be executed to use that content in the ASU Toolbox?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Question 10
Which are valid options to check the progress of the database migration in a Microsoft Windows environment?
There is correctanswers to this question.
Response:
There is correctanswers to this question.
Response:

where in SAP doc can I find the statement "Without table contents comparison, only 40 R3load processes are being started"?